SITE MEETING AT BUYOBE HEALTH CENTRE II
The District chairman LCV, CAO, CFO and DHO held a site meeting for the construction of a general ward at Buyobe HC2.
The purpose of the meeting was to monitor the progress of construction. The contractor was behind schedule and the team which prompted the District leadership to fast track the construction progress.
The CAO was impressed with the workmanship and further urged the contractor to speed up to avoid money being swept back to the consolidated fund.
He talked about the community which wasn't happy when the District bought church land to construct the Health centre. He advised them that the Health facility is a public good.
The District Engineer advised the contractor to triple his efforts and catch up with the time lines.
The LCV advised the contractor to speed up and get to roofing level and further informed the residents that the project was given to the District through the lobbying skills of Hon Amos Lugolobi Minister of state for finance.